Soil classification basis
Type A, B, or C, and where it came from: the geotechnical report, a competent person’s classification, or an assumed worst case. An unstated basis is the most common first-round comment.
You have a trench to dig or a deck to pour, and a reviewer who wants a temporary-works submittal first. We design the system, stamp it with a California PE, and package it the way public-works reviewers check it, so it comes back approved instead of with comments.
Written scope and fee within one business day.

Protective systems for excavations deeper than 20 feet must be designed by a registered professional engineer (8 CCR 1541.1 Appendix F; 29 CFR 1926.652(b) and (c)). For California work, the engineer must be California-registered.
At 20 feet or less, the Cal/OSHA tables and manufacturer tabulated data cover standard conditions only. Surcharge from spoil or equipment, adjacent structures and utilities, groundwater, layered or disturbed soil, and agency specifications that call for a stamped submittal all push a trench outside the tables. That is where most public-works trenches end up, and where we come in: a tabulated-data letter in 5 business days when the data applies, or an engineered design when it does not.
If any of these apply, plan on Tier 2 or Tier 3.
We review contractor submittals on public works. These are the items that decide whether a shoring submittal is approved or returned, and every H2 package addresses each one on its face.
Type A, B, or C, and where it came from: the geotechnical report, a competent person’s classification, or an assumed worst case. An unstated basis is the most common first-round comment.
Shown, dimensioned, and consistent with the soil type. Apparent pressure envelopes for braced systems, active and passive for cantilevers.
Equipment, spoil, traffic, and adjacent footings, with offsets and magnitudes on the plan, not buried in the calcs.
Sheeting, walers, struts, and piles checked against the demand at each depth, with the governing ratio called out.
Step by step, including when the trench may be entered and how the system is removed without loss of support.
If groundwater is present, how it is controlled and what happens to the design if it is not.
The plan names who classifies soil and inspects the system daily, per Cal/OSHA.
Tabulated data for hydraulic shores, shields, or slide rail, with the applicable tables marked.
Turnaround runs from receipt of the trench profile, utility information, and soil data.
Engineer’s letter confirming the manufacturer’s tabulated data applies to your trench, a site sketch, and a competent-person note.
Sheet pile, soldier pile and lagging, deep trench, surcharge, or adjacent structures. Calculation package with plan and section.
Plan sheets, calculations, installation and removal sequence, dewatering notes, and manufacturer data, assembled for agency review.
Revisions. Reviewer comments are answered at no additional charge. Scope changes are reflected in a revised written scope before the work.
Fixed fee, confirmed in writing before work begins. No hourly billing and no added charge for plan check responses.
We do not furnish, install, or inspect the shoring, and we do not act as the competent person. Geotechnical investigation, utility potholing, and survey are by others. After we deliver, the contractor submits the package, installs per the sequence, and the competent person inspects daily.
Falsework design for bridges, box culverts, retaining walls, and cast-in-place building elements on California public works. Caltrans falsework submittals under Standard Specifications Section 48, and local agency specifications that adopt or modify it.

Under Title 8, Section 1717(b)(1), falsework and vertical shoring need design calculations and working drawings signed by a California registered civil engineer when any one of these applies:
Below those triggers, Section 1717(b)(2) allows the plan to be signed by a registered civil engineer, a manufacturer’s authorized representative, or a qualified licensed contractor’s representative. Either way, the plan must be on site at all times.
Minimum design loads from the same section: 100 psf combined dead and live load regardless of slab thickness, with live load plus formwork at least 20 psf above the concrete weight. Lateral load at each floor is the greater of 100 lb per lineal foot of floor edge or 2% of total dead load.
On Caltrans work, falsework falls under Standard Specifications Section 48-2, with submittal and shop drawing requirements in 48-2.01C. Review takes 20 calendar days on most contracts, longer for complex structures or where railroad approval is required. Resubmittals get the same review period. Many local agencies adopt or modify Section 48, so check your spec section.
Separately, Cal/OSHA requires a permit for falsework or vertical shoring more than 36 feet high when complete, measured from the lowest surrounding grade to the soffit. That permit is the contractor’s; our drawings support it.
The Caltrans Falsework Manual (Chapter 2) lists what the shop drawings must show. If any item is missing, the reviewer must return the submittal for correction. Every H2 package shows all fifteen on the drawings.
Every load-carrying member, including soffit joists, and all transverse and longitudinal bracing with connections.
Members supporting sloping exterior girders, deck overhangs, and attached construction walkways.
Beam length and spacing, post location and spacing, bent height, and vertical spacing of diagonal-brace connectors.
Where and how the falsework is adjusted to final grade.
Concrete placing sequence or direction of pour, and every construction joint.
Every traffic, railroad, and pedestrian opening, with horizontal and vertical clearances shown.
Location of temporary railing.
Trade name and rating of any proprietary shoring system.
Maximum horizontal distance piles may be pulled into place under the caps.
Maximum deviation of piles from vertical.
Assumed soil bearing values for pads and footings.
Grade (E-value), species, and type of structural composite lumber, with the manufacturer’s working stress values.
The welding standard for any welded member.
Seal and signature on each sheet where a Section 1717 trigger applies, including the contractor’s standard plans and details.
The contractor’s design calculations and supplemental data.
Drawings, not calc sheets. A detail sketched on a calculation sheet must also appear on the shop drawings. Reviewers will not complete a review by referring to the calculations.
Completeness comes first. Reviewers check completeness within about two working days. An incomplete package goes back before the 20-day review even starts.
Turnaround runs from receipt of the structure drawings, the specification section, and soil information.
Engineer’s letter confirming a contractor-proposed or supplier-proposed system meets the specification and the safety order for a specific configuration, with supporting calculations.
Calculations, plan and elevation sheets, member sizing, bracing layout, bearing and sill design, camber, pour sequence, and removal sequence.
Design package for falsework spanning an open traffic lane, including clearance envelopes, impact protection where required, and the agency’s traffic-opening requirements.
Section 1717(c)(1) site inspection after erection and before concrete placement, with written certification that the falsework substantially conforms to the working drawings and that material and workmanship are satisfactory.
Revisions. Reviewer comments are answered at no additional charge. Scope changes are reflected in a revised written scope before the work.
Fixed fee, confirmed in writing before work begins. No hourly billing and no added charge for plan check responses.
Pick the service, then give us what you have. If the spec section is handy, include it.